Project percent remains at zero % Issue

CarolanIS
CarolanIS
Offline
0
Hello,
My project percentage is remaining at zero no matter how many hours are associated with the project. Also, on the front end, the project status bar is not populating.

Please advise.
Responses (2)
  • Accepted Answer

    CarolanIS
    CarolanIS
    Offline
    Wednesday, November 01 2017, 10:28 PM - #Permalink
    0
    Thank you, I was not associating completed tasks due to the duration.
    The reply is currently minimized Show
  • Accepted Answer

    Thursday, October 19 2017, 09:35 AM - #Permalink
    0
    you are associating the hours via TASKS, and marking those tasks as "completed" ?
    The reply is currently minimized Show
Your Reply